Section 202.6 Amended ID #2012-006R

Purpose

The AESO is seeking Stakeholder feedback on Appendix 3 and the removal of the exclusion of wind and solar generation from the detailed calculations and methodologies relating to long-term adequacy of supply contained in Information Document #2012-006R, Adequacy, Supply Shortfall and Energy Emergency Alerts ("Amended ID 2012-006R").

On October 26, 2022, the Alberta Utilities Commission approved amendments to Section 202.6 of the ISO rules, Adequacy of Supply. During the proceeding, the AESO committed to engaging Stakeholders on the initial release of Amended ID #2012-006R.

Purpose

The AESO is seeking Stakeholder feedback on Appendix 3 and the removal of the exclusion of wind and solar generation from the detailed calculations and methodologies relating to long-term adequacy of supply contained in Information Document #2012-006R, Adequacy, Supply Shortfall and Energy Emergency Alerts ("Amended ID 2012-006R").

On October 26, 2022, the Alberta Utilities Commission approved amendments to Section 202.6 of the ISO rules, Adequacy of Supply. During the proceeding, the AESO committed to engaging Stakeholders on the initial release of Amended ID #2012-006R.

  • Written Consultation | Jan. 10 - 24, 2023

    This consultation has concluded.

    Purpose

    The AESO received stakeholder feedback on Appendix 3 and the removal of the exclusion of wind and solar generation from the detailed calculations and methodologies relating to long-term adequacy of supply contained in Information Document #2012-006R, Adequacy, Supply Shortfall and Energy Emergency Alerts ("Amended ID 2012-006R").

    On October 26, 2022, the Alberta Utilities Commission approved amendments to Section 202.6 of the ISO rules, Adequacy of Supply. During the proceeding, the AESO committed to engaging Stakeholders on the initial release of Amended ID #2012-006R.

    AESO Reponses to Stakeholder Comments

    Written comments received from Stakeholders in response to the AESO's January 10, 2023, Letter of Notice regarding Amended ID #2012-00R have been posted and responses to those comments have been posted as well. Thank you to all Stakeholders who participated in this consultation.

    Written Consultation materials

    Can be found in the AESO Materials and Stakeholder Submissions sections.