Lifecycle Activities | 2021-2022
CLOSED: This discussion has concluded.
Post-Disposition | June to December 2022
- File post-disposition letter with AUC Proceeding 27047 indicating AESO's plans regarding AMP (June 2022)
- Update stakeholders on post-disposition AMP plans (Dec 2022)
AUC Proceeding 27047 | AUC Process
- AUC Proceeding 27047
- Commission issued Decision 27047-D01-2022, denying the AESO's application for approval to implement the AMP (May 2022)
Notice for Development | October to December 2021
- Consult with stakeholders on proposed AMP Implementation and corresponding amendments to Section 502.10 (Oct to Nov 2021)
- File application for approval of proposed AMP Implementation and Amendments to Section 502.10 with the AUC (Dec 2021)